New Church Construction — March 2007
First week of March — The outer edge of the foundation
has been poured and the interior slab is now ready to be poured. Before that happened, on March 4, 2007 Fr. Vicente conducted
a blessing of the foundation, spreading of sacred soils collected from around the world by parishioners, and sprinkling of
water from the Jordan River. A short story about the blessing and a photo similar to below made the front page of the Wet
Mountain Tribune for the week of March 8-14, 2007.


Third week in March—main foundation was poured and cured, followed by the construction of the first walls. These will be lifted into position by a crane during the last week of March. 




Forth Week in March—more walls were constructed and then the on Friday, March 30 the erection of walls began.




|
|